Probewell | WT Series | What is a Full test?

What is the Full test?




Full Test

How does it work?
The Full test is used to fully assess the quality of a meter, as it runs a complete sequence of sub-tests.
The Full test runs an equivalent of the Quick Test followed by additional single-element tests.

To execute a Full test, an optical pickup or a metercam must be installed on the WT series tester.
The sub-tests are:
  1. All phases - High Load (HL),
  2. All phases - Power Factor (PF),
  3. All Phases - Low Load (LL),
  4. Phase A - High Load (HL),
  5. Phase A - Power Factor (PF),
  6. Phase A - Low Load (LL),
  7. If applicable
    1. Phase B - High Load (HL), 
    2. Phase B - Power Factor (PF),
    3. Phase B - Low Load (LL).
  8. Phase C - High Load (HL),
  9. Phase C - Power Factor (PF),
  10. Phase C - Low Load (LL)
Once the test is completed, the user may save the test data in the device memory.


    • Related Articles

    • What is Demand test?

      Demand test Ho does it work? The Demand test is used to test meters that have a demand register, (no accessories are needed). The meter must first be configured to be in kW demand test mode (check meter manual for device specific procedure). The ...
    • What is the Custom test?

      Custom Test How does it work? The Custom test is used to test a specific combination of load and active phase. Once the test is completed, the user can save the test data in the device memory. To execute a Custom test, an optical pickup or a Metercam ...
    • When the memory is full does it start overwriting the old tests automatically or does it notifies the user that the memory is full before starting to overwrite?

      The test data is never overwritten when the socket runs out of storage. The socket will generate an error and will indicate the user that he need to export test data to a PC. When the user is to save the 101th test, it will display a message saying : ...
    • What is the Quick test?

      Quick test What is a Quick test? The Quick test can be used to quickly assess the accuracy of a meter. How does it work? The Quick test runs a predetermined sequence of sub-tests, all in one operation, during which all phases are energized ...
    • What is Four Quadrant test (4 Quad Test)?

      What is a Four Quadrant test? The Four Quadrant test is an automatic test sequence that can be used to assess the meter’s ability to register energy in all four quadrants of the power vector diagram. The Four Quadrant Test runs an equivalent of the ...